BS EN 61439 explained: what it means for your control panel
The standard behind almost every low-voltage panel built in the UK, what design and routine verification actually involve, and what you should specify.
Read the articleIf your machine is heading to the US or Canada, the panel has to meet UL 508A. Here is what changes from UK practice and how to plan for it.
More and more UK machine builders are shipping to the US and Canada, and the control panel is often the part that causes the most surprises. A panel that’s perfectly good for a UK factory can be rejected on a North American site because it doesn’t meet the local rules. The standard you need to know is UL 508A.
In the US, electrical installations are inspected against the National Electrical Code (NFPA 70), and industrial machinery is also expected to follow NFPA 79. Local inspectors, known as the authority having jurisdiction, generally expect to see industrial control panels that are certified to UL 508A, the standard for industrial control panels. Without that certification, a panel may need expensive field evaluation or rework on site, often at the worst possible time in a project.
For Canada, panels are assessed against the Canadian standard CSA C22.2 No. 286. If your machine is going to Canada, check that the certification covers Canada as well as the US.
Components in a UL 508A panel need to be UL Listed or Recognised for the way they’re being used. Many European components carry dual approvals, but the detail matters. A common example is circuit protection: a miniature circuit breaker listed to UL 489 can be used for branch circuit protection, but a device only recognised as a supplementary protector under UL 1077 cannot. Getting this wrong is one of the most common reasons a panel fails review.
Wire is sized in AWG rather than square millimetres, and conductor types and ratings have to suit the application. Colour coding also follows North American practice rather than the UK harmonised colours. Typical NFPA 79 conventions are:
| Colour | Typical use |
|---|---|
| Black | Ungrounded AC and DC power conductors |
| Red | Ungrounded AC control circuits |
| Blue | Ungrounded DC control circuits |
| Orange | Circuits that stay live when the main disconnect is off |
| White or grey | Grounded (neutral) conductors |
| Green, or green and yellow | Equipment grounding (earth) |
Every UL 508A panel must be marked with its short-circuit current rating. The SCCR is worked out from the ratings of the components in the power circuits and the protective devices ahead of them, and the weakest link often sets the rating for the whole panel. If the site’s available fault current is higher than the panel’s SCCR, the panel can’t be installed, so it’s worth knowing the site requirement early.
UL 508A has its own requirements for spacings between live parts, for the main disconnect and its interlocking, and for the markings and information that must appear on the panel. None of this is difficult, but it needs designing in from the start rather than adding at the end.
There are two common routes. A panel shop can be listed under the UL 508A programme and apply the mark itself, or a panel can be inspected and certified by an independent third-party certification body. At Pro Panel Build we build UL 508A panels in our Warwickshire workshop, and each one is inspected and certified professionally by our third-party certification partner before it leaves.
Keep reading
Practical guides for engineers and buyers.
The standard behind almost every low-voltage panel built in the UK, what design and routine verification actually involve, and what you should specify.
Read the articleThe drawings, details and decisions that turn a rough budget into a firm price, and what to do if you don’t have everything yet.
Read the article